
About This Page
This page is dedicated to recording the progress of the extraordinary project to construct a third crossing of the Cataraqui River in Kingston, Ontario. Started in 2020, it will reach its conclusion in 2023, when all the cosmetic work is completed.
The major effort on the new bridge will occur this year - 2021 - with the arrival and installation of girders and the construction of the under-arched steel bridge section closest to the eastern shore.
I hope you'll enjoy viewing the images - please credit me - Aerosnapper, Kingston - with producing them if you use any of them.
Photos
A fine sight on a Winter's night
The Waaban Crossing looks very with the reflections of its lights and neighbouring area reflecting in the icy waters of the Cataraqui River
Final Adjustments on the Vibro Hammer
July 2022 - Kiewit staff confirm attachment of the vibrating hammer to the first pile to be withdrawn as the disassembly and removal of the temporary trestle roadway gathers pace
Team work makes the dream work
Dec 2022 - Workers from Utilities Kingston prepare a transformer for installation to ensure adequate power to the area of the bridge
A view to the South-West over the City
Sep 2022 - The waterproofing of the western concrete spans can be clearly seen - asphalt paving will follow shortly
All coming together quite nicely
July 2022 - the addition of hydro-seeded margins to the recently road-marked intersection of Gore Road and Hwy 15 makes everything look better and closer to completion
Can't do the job without humans
April 2022 - as the pumper delivers concrete steadily, it is directed down into the rebar and raked, whilst a backpack vibrating rod ensures the release of any trapped air that could weaken the slab
Concrete forms removed from the east abutment
Mar 2022 - a large number of concrete forms used in the fourth stage pour of the east abutment wait to be organised and removed on Gore Road, with the bridge beyond.
Linking east and west across a frozen river
Dec 2022 - a day after it opened to the public, the Waaban Crossing stands out as a new landmark in the City of Kingston
Early morning looking North- East
Sep 2022 - The waterproofing applied to the western spans is clearly evident. Otherwise, the bridge is looking very clean and clear in its last months of construction
The whole bridge - early morning
April 2022 - the concrete on the steel span is complete and the east abutment is nearing complete infill as the trees begin to come into leaf
A Large Section of Concrete is added to the Main Span
April 2022 - a break in the weather allows CBM and Maple Concrete Pumping to service the Gomaco machine as it lays a long swathe of concrete on the main steel span
Early Moments of the latest concrete pour
April 2022 - the long arm of Maple Concrete Pumping's concrete delivery truck provides a steady flow of concrete to the main steel span, where the Gomaco screeding machine and a capable crew ensure it is applied efficiently
The mighty seven-axled concrete pumper
April 2022 - this powerful, long-armed pump truck makes light work of delivering concrete to the steel span
The last two spans in late stages of completion
Mar 2022 - walkways are being built on Span 21 and the first concrete deck slabs are in place on Span 21. All part of an effort to prepare for rebar, then concrete and, last of all, the asphalt top layer